28/04/2025 - Power Plant Offer - Alstom GT13 DM EV 103MW Gas Turbine + Brown, Boveri & Cie Steam Turbine 50MW - COMBINED CYCLE 150MW POWER PLANT


28/04/2025 - Power Plant Offer - Alstom GT13 DM EV 103MW Gas Turbine + Brown, Boveri & Cie Steam Turbine 50MW - COMBINED CYCLE 150MW POWER PLANT

Inquire

Catalog #176290

Catagory: Plant and Equipment  -- Power Generation
Dragon's Price: CONTACT US
Date Added: May 08, 2025 23:41

28/04/2025 - Power Plant Offer - Alstom GT13 DM EV 103MW Gas Turbine + Brown, Boveri & Cie Steam Turbine 50MW - COMBINED CYCLE 150MW POWER PLANT



Sale Offer: 150 MW Gas-Fired Power Plant in Austria



Direst to exclusive agent to sell this 150 MW gas-fired power plant located in Austria.



The plant is in exceptional condition, with low operating hours and ready for immediate operation.



Below are the key details:



Facility Overview

Type: Combined Cycle Power Plant



Location: Austria



Condition: Very good, well-maintained, and operational at any time.



Capacity: 150 MW (Gas Turbine: 103 MW; Steam Turbine: 47 MW)



Efficiency: Electrical efficiency of 50%



Startup Time: Full load achievable within 25–120 minutes



Load Gradients:



Gas turbine: 7.9 MW/min



Combined block: 8.5 MW/min



Historical Highlights

1980: Facility upgraded to a combined cycle unit with an output of 125 MW. Efficiency achieved: 47.9% (world-leading at the time).



2003-2005: Replacement with a more powerful gas turbine, increasing capacity to 158 MW.



Design Excellence: Combines a gas turbine and forced circulation boiler for steam generation with a steam turbine.



Technical Specifications

Gas Turbine: Alstom GT13 DM EV (103 MW, ISO standards)



Waste Heat Boiler: Wagner Biro (dual-pressure, forced circulation design)



Steam Turbine: Brown, Boveri & Cie - BBC (50 MW, single-shaft condensing turbine with dual-pressure feed)



Grid Integration

The power generated is fed into the 110 kV grid through a dedicated substation and overhead line.



Pricing & Additional Details

Total Price (Including Spare Parts): €35 Million EUR



Spare Parts Value: €10 Million EUR (due for major turbine service in approx. 10,000 operating hours)



Dismantling Costs: €4.8 Million EUR



Transport to Port Koper, Slovenia: €960,000 EUR



Includes 10 heavy transports (total: €234,000 EUR)



Total Dismantling and Transport Cost: €5.994 Million EUR



Brand New Plant Cost Estimate: Over €200 Million EUR (calculated at €1.4M per MW for 150 MW)



Site Visit

Visits can be arranged promptly at the Austrian site. Please note that an LOI (Letter of Intent) and POF (Proof of Funds) with 5% deposit into escrow are required for appointment scheduling.



Should you have any questions or require further information, please do not hesitate to contact me. I look forward to hearing from you!



#greg

Inquire
ADDITIONAL INFORMATION


People That Have Inquired On
This Item Also Liked:

18 - 2021 International LT 625 Sleepers JENBACHER J 620 GS - NL For Sale - Ref : INDR/IVI - 2 2x Solar Turbines:Titan130,15mw,Year:2008,hours:127 - Ref : P/AA -87 2) CAT TL1055 Telehandlers! 2011 Grove GMK5275 All-Terrain Crane 2011 LIEBHERR LTM1350-6.1 400 US Ton (350 Metric Ton) All Terrain Crane 2021 Volumetric KW T880 Truck